  • This riding arena needed to be expanded, defined and required new footing
  • The existing arena had pretty good drainage, so the grading was minor
  • We removed the topsoil in the area to be expanded
  • Then we installed rail road ties to define the arena
  • We added stone base in the expanded area
  • Then we installed 4″ of course sand footing (as per Owner’s instruction)
  • We graded and re-stoned the entrance path
  • Finally, we installed a simple fence to define the entrance to the arena